67

Tonnes of Material

4205

Parts

381

Assemblies

The Project Outline

One of three buildings steel detailing was provided for over the 2019 Christmas break to meet our clients tight schedule.

This was also the largest of the three and Included several features such as an internal mezzanine and two re-fueling bays.

We where able to utilize Tekla and provide updated IFC models to our client over the course of the design to keep them up to date as well as there client and exchange notes via BIMsite.

Location
Horsley Park,
NSW
Member Types
  • Columns
  • Rafters
  • Rod bracing
  • Pre-set rafters
  • Rurlins
  • Girts
  • Welded facia purlins
Year

2019